Multi-Phase Project: Phase
TVA Chickamauga Relief Hole
The Brayman Construction Foundations Division was subcontracted by the Tennessee Valley Authority (TVA) for specialty drilling services at the Chickamauga Dam.
location
Chattanooga
,
Tennessee
ESTIMATED VALUE
$500k
owner
Tennessee Valley Authority
Completion date
general contractor
Brayman Construction
Market
Locks & Dams
Multi-Phase Project: Phase
TVA Chickamauga Relief Hole
The Brayman Construction Foundations Division was subcontracted by the Tennessee Valley Authority (TVA) for specialty drilling services at the Chickamauga Dam. In total, 5-each, 100-lf deep holes were reamed to a larger diameter in tight drilling conditions and difficult downhole conditions in order to create relief holes in the dam for future saw cutting.
OUR PROJECTS
Related Projects
Multi-Phase Project
Chickamauga Lock Monolith M48 Anchors
Project consists of 60,000 CY of rock excavation, 65,000 CY common excavation, over 100,000 CY embankment material, 90,000 CY of mass concrete and over 1,150 high capacity dam anchors. It will also include a grout curtain and reconstruction of the left and right river banks.
Multi-Phase Project: Phase
5
Bluestone Dam
Project consists of 60,000 CY of rock excavation, 65,000 CY common excavation, over 100,000 CY embankment material, 90,000 CY of mass concrete and over 1,150 high capacity dam anchors. It will also include a grout curtain and reconstruction of the left and right river banks.
Multi-Phase Project: Phase
5 Cofferdam
Bluestone Dam
A sheet pile cofferdam was installed down the center of the existing stilling basin to divide the spillway in half in preparation for the Phase 5 Spillway Reconstruction Project.
Multi-Phase Project: Phase
3
Bluestone Dam
Brayman was contracted to provide specialty construction services in support of the Dam Safety Assurance (DSA) Phase 3 Project at Bluestone Dam.
Multi-Phase Project: Phase
1 & 2
Dover Dam
Post tension anchors, spillway access platforms, underwater anchors, increased dam height via post tensioned pre-cast panels, 2 mile access road, shoring, caissons, soil nail wall, this job had it all.
Multi-Phase Project: Phase
2B
Bluestone Dam
This project involved the installation of 212 high capacity rock anchors, ranging from six to 61 strands, to upgrade the stability of the existing dam.
Multi-Phase Project: Phase
Holtwood Boat Barrier
Brayman was contracted to install underwater anchors to hold a new half mile long boat barrier.
Multi-Phase Project: Phase
Chickamauga Lock Monolith M48 Anchors
Brayman Construction was contracted to install five, 61-strand, restressable anchors to drill depths up to 195 feet in a monolith of the lock chamber at Chickamauga Lock and Dam in Chattanooga, TN.
Multi-Phase Project: Phase
North Fork Spillway Soil Nail Wall
Brayman was subcontracted to install a 5719 SF soil nail wall as part of a spillway expansion project at the North Fork Dam near Black Mountain, NC. Both soil nails and tieback anchors were installed on this wall which served as a slope stabilization measure for construction of a permanent access road on the site.
Multi-Phase Project: Phase
Prettyboy Dam
The Prettyboy Dam project involved the installation of an underwater anchorage system necessary to secure the concrete gatehouse to the dam.
Multi-Phase Project: Phase
Bagnell Dam Stabilization
The dam received a structure upgrade in 2018, which included over 16,000-cy of mass concrete, 68-ea high capacity dam anchors, and 175-ea drains.
Multi-Phase Project: Phase
Lake Scranton Dam
Twenty-three post tensioned dam anchors were installed to upgrade capacity of the dam while working around multiple other sub-contractors in very tight access.
Multi-Phase Project: Phase
Charleroi Locks & Dam - River Chamber Completion
The modernization effort at this site will ultimately result in the construction of two new 84-feet wide by 720-feet long chambers to replace the existing 56-feet wide lock currently in operation.
Multi-Phase Project: Phase
North Carolina Hydro Dam
Ten vertical drain holes were core drilled from the crest of the dam 120 feet deep into the dam.
Multi-Phase Project: Phase
Charleroi Locks & Dam Emptying Basin
The project scope involves building seven, separate precast concrete structures offsite, then loading the segments onto barges, delivering them to the job site, and assembling them into place, under water, using floating A-frame cranes.
Multi-Phase Project: Phase
Hawks Nest Dam
Brayman was selected to install 50 epoxy coated dam anchors, which upgraded the structure to current federal dam safety standards.
Multi-Phase Project: Phase
Nesbitt Dam
This project exemplified Brayman's ability to offer "one stop shopping" for construction services by featuring several capabilities including high capacity dam anchors, temporary shoring, and driven piling.
Multi-Phase Project: Phase
Charleroi Locks & Dam - New River Wall
The new River Wall project is a component of a larger effort to improve and modernize the navigation facilities on the Lower Monongahela River between Braddock and Charleroi.
Multi-Phase Project: Phase
Paddy Creek Dam
Brayman was contracted to provide specialty construction services in support of a safety improvement project located at Paddy Creek Dam on Lake James near Nebo, NC.
Multi-Phase Project: Phase
Cliffside CCP Low Head Dam Modifications
Brayman Construction was awarded a contract to provide specialized construction services in support of a dam improvement project located on the Broad River in Cleveland County, North Carolina.
Multi-Phase Project: Phase
Dan River CCP Low Head Dam Modifications
Brayman Construction was awarded a contract to provide specialized construction services in support of a dam improvement project located on the Dan River near Eden, North Carolina.
Multi-Phase Project: Phase
Kerr Dam Spillway Stabilization
The Kerr Dam Spillway Stabilization Project includes one pre-production post-tensioned rock anchor on the top of the dam, 48 production post-tensioned anchors across the downstream face of the spillway, and a temporary platform for access to the spillway locations.
Multi-Phase Project: Phase
TVA Chickamauga Relief Hole
The Brayman Construction Foundations Division was subcontracted by the Tennessee Valley Authority (TVA) for specialty drilling services at the Chickamauga Dam.
Get in Touch
Interested in Partnering or Joining Our Team? Connect with us to explore opportunities for collaboration and career growth at Brayman Construction.