Brayman Projects

Blueprints to Reality:
A Showcase of Brayman’s Portfolio

Brayman Projects header image

We Have A Passion For Building Great Works

At Brayman Construction, we take pride in our wide-ranging project portfolio, from large-scale complex bridges, deep foundations, marine and dam construction and rehabilitation, complex and heavy steel erection and rehabilitation, and demolition services. Our proven capabilities in these projects demonstrate our diverse skill set in tackling some of the most challenging projects in the industry.

Projects Filter
Tag
Showing 0 of 100
Projects Filter
Client Type:
Clear Client Types
Locations:
Clear Locations
Capabilities:
Clear Capabilities
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
VIEW RESULTS
View Results
Project consists of 60,000 CY of rock excavation, 65,000 CY common excavation, over 100,000 CY embankment material, 90,000 CY of mass concrete and over 1,150 high capacity dam anchors. It will also include a grout curtain and reconstruction of the left and right river banks.
location
market
Client Type
Brayman Construction Corporation (BCC) was contracted by the Virginia Department of Transportation (VDOT) to provide design, Quality Control/Quality Assurance Management (QC/QAM), and construction services for the I-77 Over Route 606 Bridge Replacement project in Bland County, VA.
location
market
Client Type
Brayman Construction Corporation and Trumbull Corporation, a Joint Venture (BTJV), was contracted to provide design and construction services for the $254 million U.S. 35/I-64 Interchange – Nitro Interchange Design-Build Project. Brayman served as the lead contractor in this Joint Venture.
location
market
Client Type
The new memorial bridge replaced an existing pedestrian and golf cart bridge over a small lake on the course and was designed around the existing bridge members. The project site had very limited laydown and work area available, so the Demolition, Steel Erection, and Precast Installation was all marine-based and completed from the lake surrounding the new bridge.
location
market
Client Type
The Mon/Fayette Expressway, a critical infrastructure project with planning origins tracing back to the 1950s, continues its development toward completion. The Brayman Construction Foundations Division, was subcontracted by Trumbull Corp to execute the installation of micropile foundations for the latest section of this expansive expressway, Section 53A1.
location
market
Client Type
Brayman and Shoreline Foundation, Inc. of Miami, Florida, were contracted by Kingston Wharves Limited to design and reconstruct Berth 7 at the Port of Kingston in Kingston, Jamaica. This project was a Joint Venture in which Brayman was the lead contractor.
location
market
Client Type
Brayman Foundations Division was subcontracted to provide a Design-Build micropile foundation solution for the new U.S. Customs and Border Protection (USCBP) Integrated Design and Construction/Design Learning Center (IDC/DLC) Facility in Harpers Ferry, WV.
location
market
Client Type
Brayman Construction was awarded a contract to provide specialized construction services in support of a dam improvement project located on the Broad River in Cleveland County, North Carolina.
location
market
Client Type
Brayman Construction Corp. (BCC) was subcontracted by Advantage Steel and Construction, LLC to perform a repair procedure involving a new anchorage system to attach the suspension cable at one corner of the Wheeling Suspension Bridge.
location
market
Client Type
The Brayman Team completed the drilling and installation of 1250 Nails and installed 29,000 SF of shotcrete as part of the CONSOL Coal Refuse Disposal Area 7 Project in Greene County, Pennsylvania.
location
market
Client Type
This Cadiz Ohio slope repair project was a crucial endeavor aimed at preventing further strain on an adjacent pipeline.
location
market
Client Type
location
market
Client Type
Brayman Construction Corporation (Brayman) was subcontracted to provide specialty geotechnical construction services in support of the Elmhurst Innovation Center project located in Pittsburgh, PA.
location
market
Client Type
Brayman Construction was awarded a contract to provide specialized construction services in support of a dam improvement project located on the Dan River near Eden, North Carolina.
location
market
Client Type
Brayman Construction was awarded a $20.5 million design-build Accelerated Bridge Construction (ABC) contract for a multi-bridge project consisting of 8 bridge deck replacements and 2 specialized overlays along the busy I-77 and I-64 corridor in Charleston, WV that had to be completed in an extremely short timeframe.
location
market
Client Type
Installation of an 80' deep tied back retaining wall.
location
market
Client Type
The Brayman Construction Foundations Division was subcontracted by Turner Construction for micropile foundations at the historic Ford Factory in the East Liberty neighborhood of Pittsburgh, PA.
location
market
Client Type
This project consists of four and one-half feet drilled Shafts at the abutments and six and one-half feet drilled shafts at the river piers.
location
market
Client Type
A sheet pile cofferdam was installed down the center of the existing stilling basin to divide the spillway in half in preparation for the Phase 5 Spillway Reconstruction Project.
location
market
Client Type
Brayman was contracted to install underwater anchors to hold a new half mile long boat barrier.
location
market
Client Type
Brayman was subcontracted to provide specialty geotechnical construction services in support of a roadway and bridge reconstruction project located between milepost 39.62 and milepost 44.04 along the Pennsylvania Turnpike in Allegheny County, PA.
location
market
Client Type
The Brayman Construction Foundations Division was subcontracted by Markwest Midstream to execute the installation of micropile foundations for a new Cryogenic plant in Smithburg, WV.
location
market
Client Type
Installation of 21 micropiles through the existing footer and 24 tiebacks through the existing wall. The micropiles and tiebacks will be tied together with a new retaining wall poured in front of the existing retaining wall.
location
market
Client Type
Brayman Construction was contracted to install five, 61-strand, restressable anchors to drill depths up to 195 feet in a monolith of the lock chamber at Chickamauga Lock and Dam in Chattanooga, TN.
location
market
Client Type
This project consisted of replacing two concrete bridge decks with a contracted time of 225 hours.
location
market
Client Type
Brayman’s work consisted of the installation of four drilled sump foundations and as well as 250 concrete spread footers, pedestal supports, wall piers, building foundations, and containment slabs to support the various equipment for the gas processing facility.
location
market
Client Type
Twenty-three post tensioned dam anchors were installed to upgrade capacity of the dam while working around multiple other sub-contractors in very tight access.
location
market
Client Type
The New River Parkway is a Heavy Civil Project encompassing the construction of just over five miles of new roadway, while maintaining traffic along the New River in Hinton, WV.
location
market
Client Type
Brayman was subcontracted to install a 5719 SF soil nail wall as part of a spillway expansion project at the North Fork Dam near Black Mountain, NC. Both soil nails and tieback anchors were installed on this wall which served as a slope stabilization measure for construction of a permanent access road on the site.
location
market
Client Type
Brayman has completed two of the three bridges in 2017 including Romigh Road Bridge which is a two lane 80-feet long span, and Snake Run Bridge which is a three lane 123-feet span. Brayman is set to complete the third and final Park Quarry bridge in summer of 2018.
location
market
Client Type
The project required the installation of 578 micropiles with diameters of five and one-half-inch, seven-inch, and nine and five-eights-inch, and depths ranging from 30 feet to over 100 feet.
location
market
Client Type
Brayman was contracted by a midstream operator to complete the micropile installation at their new gas processing Cryogenic and De-Ethanizer facility located in Washington County, PA.
location
market
Client Type
The Allegheny County Sewer Authority awarded Brayman the emergency procurement contract to repair and replace the A-34 Diversion Structure located along the Allegheny River in the Lawrenceville neighborhood of Pittsburgh, PA.
location
market
Client Type
Ten vertical drain holes were core drilled from the crest of the dam 120 feet deep into the dam.
location
market
Client Type
Nine 5/8th inch micropiles were installed under an active high-speed rail line with no interruption to rail service.
location
market
Client Type
The project consisted of the replacement of the existing two-span adjacent box beam superstructure, with a two-span continuous composite steel plate girder bridge.
location
market
Client Type
Brayman Construction was contracted to perform the $25.4 million rehabilitation of the 7th Street “Andy Warhol” Bridge for the Allegheny Department of Public Works.
location
market
Client Type
This award winning new bridge is a cable stay structure with 326’ tall delta shaped towers and a 900’ main span (the longest span ever constructed by ODOT).
location
market
Client Type
Brayman’s scope of work involved installation of a 335-feet long driven sheet pile retaining wall along the Elk River, as well as installation of a temporary 35-feet long sheet pile wall outside of the high water mark.
location
market
Client Type
Brayman's scope of work required the installation of 318-each caissons comprising 239-each, 60-inch diameter; 58-each, 54-inch diameter; 18-each, 48-inch diameter; and 3-each, 42-inch diameter shafts.
location
market
Client Type
The new 130-feet long two-lane bridge consisted of a single-span steel beam five-girder structure with new abutments supported by drilled caissons and rock anchors.
location
market
Client Type
Brayman was subcontracted to provide specialty geotechnical construction services in support of the 414 Light Street Apartment Complex project located at the corner of Light and Conway Streets on the edge of the Inner Harbor seaport of Baltimore, MD.
location
market
Client Type
Brayman’s scope of work required installation of a secant pile excavation support system comprised of 152-each, 48-inch diameter interconnecting secant piles (12,309-LF) with depths up to 91-feet, as well as installation of 150-each, 18-inch diameter augercast piles for structure foundation support.
location
market
Client Type
The McKnight Road project involved bridge rehabilitation, including deck replacement, of four structures along a stretch of road infamously known locally for traffic congestion.
location
market
Client Type
The Pennsylvania Department of Transportation’s replacement of the SR 30 Bridge near East Pittsburgh, PA, was comprised of the complete demolition of the existing superstructure, replacement of abutment stems, installation of precast deck modules, and setting of sleeper and approach slabs.
location
market
Client Type
The Lilly Bridge project involved replacement of a cantilever truss bridge with a new 1,220-LF five-span, fabricated steel girder bridge.
location
market
Client Type
Brayman’s scope of work included installation of soldier beams, and tiebacks anchors while working closely with other contractors on precast panel installation and backfilling activities.
location
market
Client Type
Brayman’s scope of work included installation of 11-each large diameter shafts, up to 240-feet deep and 42-inch diameter, which will be used for various utilities.
location
market
Client Type
Work consisted of 2 temporary "fill walls", needed to support the existing roadway in fill areas until new MSE walls could be constructed and 2 permanent "cut walls", needed in areas where the new third lane construction required cutting existing embankments.
location
market
Client Type
The Pennsylvania Department of Transportation’s Replacement of the Hulton Bridge near Oakmont, PA, involved the replacement of a two lane truss bridge with a new 1,633 LF four lane five span haunched girder bridge erected upstream of the existing bridge on the Allegheny River.
location
market
Client Type
The new 338-feet long two-lane bridge was constructed with the substructure founded on cast-in-place concrete pipe piles.
location
market
Client Type
The project scope involves building seven, separate precast concrete structures offsite, then loading the segments onto barges, delivering them to the job site, and assembling them into place, under water, using floating A-frame cranes.
location
market
Client Type
The Masontown Bridge project involved the replacement of an existing 11-span, two lane steel truss structure with a new 1,700-LF 7-span four lane plate girder bridge.
location
market
Client Type
The project consisted of two phases. Phase 1 involved the installation of an anchored sheet pile retaining wall and the installation of eight 120-inch diameter caissons. Phase 2 included the installation of structural steel beams and the construction of a 120-foot by 46-foot concrete deck.
location
market
Client Type
Post tension anchors, spillway access platforms, underwater anchors, increased dam height via post tensioned pre-cast panels, 2 mile access road, shoring, caissons, soil nail wall, this job had it all.
location
market
Client Type
Brayman was selected to install 50 epoxy coated dam anchors, which upgraded the structure to current federal dam safety standards.
location
market
Client Type
Brayman was contracted to replace the existing seven-span steel truss Greensburg Pike Bridge carrying SR 7467 over Turtle Creek and three active Norfolk Southern rail tracks located in Allegheny County, PA.
location
market
Client Type
The Rodney Staton Memorial Bridge project involved the design-build rehabilitation of a 630-LF, three span structure spanning R.D. Bailey Lake.
location
market
Client Type
This project consisted of a new four-span steel structure bridge for CSX Railroad, located in Youngstown, Ohio.
location
market
Client Type
Not only was our team able to prevent the roadway from sliding into Ten Mile Creek, we also prevented an ensuing road closure accompanied by a 35-mile traffic detour.
location
market
Client Type
Brayman was contracted to install precast concrete coffer boxes around the pipe to allow for easier access to the pipe for cleaning operations.
location
market
Client Type
Brayman Construction was subcontracted to provide specialty geotechnical services in support of the construction of a new four story, 60,000-sf hospital located on 2.6 acres in South Fayette Township, PA.
location
market
Client Type
Brayman's scope of work required installation of an 800-foot, tieback-anchored soldier beam and lagging wall, comprised of 99-each soldier beams; 91-each, 7-strand and 8-strand Class I corrosion protected anchors; and 15,000-SF of mixed 4-inch thick hardwood lagging.
location
market
Client Type
When a portion of the northwest wingwall collapsed, the Maryland DNR and DGS contracted with Brayman for an emergency stabilization. The remediation included salvaging the original facing stones, removing the existing bridge deck, and excavating 9 feet below deck elevation.
location
market
Client Type
The Ices Ferry Bridge project involved the replacement of a steel through-truss bridge with a new 960-LF four-span steel girder bridge located near Morgantown, WV.
location
market
Client Type
The Pennsylvania Department of Transportation awarded Brayman to rehabilitate the existing Strank Bridge located in Johnstown, PA.
location
market
Client Type
Brayman was contracted by PennDOT to widen PA State Route 28, section A50, located near downtown Pittsburgh.
location
market
Client Type
This project exemplified Brayman's ability to offer "one stop shopping" for construction services by featuring several capabilities including high capacity dam anchors, temporary shoring, and driven piling.
location
market
Client Type
This project involved the installation of 212 high capacity rock anchors, ranging from six to 61 strands, to upgrade the stability of the existing dam.
location
market
Client Type
Brayman was subcontracted to provide specialty construction services in support of a Headworks Facility and Primary Clarifier project located in Hamarville, PA.
location
market
Client Type
The new River Wall project is a component of a larger effort to improve and modernize the navigation facilities on the Lower Monongahela River between Braddock and Charleroi.
location
market
Client Type
Brayman’s scope of work required installation of deep foundation systems for the elevated guideways and stations.
location
market
Client Type
Brayman was contracted to provide specialty geotechnical services to Heartland Homes, Inc. for this residential land development project located 15 miles south of Pittsburgh at the Hiddenbrook Development Plan in Peters Township, PA.
location
market
Client Type
Brayman was contracted by the WV Division of Highways to construct a new 2,975’ long concrete segmental bridge outside of Charleston, WV to carry eastbound I-64 over the Kanawha River.
location
market
Client Type
As part of the third lane expansion of the Pennsylvania Turnpike from MP 67.59-MP 74.59, Brayman performed 30,000-ft of drilling and onsite batching of 16,000-cy of grout to stabilize an abandoned coal mine adjacent to the roadway.
location
market
Client Type
Completion of this project further extends Allegheny County’s Light Rail System from underneath downtown Pittsburgh and the Allegheny River to the North Shore.
location
market
Client Type
Brayman Construction Corporation was contracted by PENNDOT to repair and strengthen the existing Freeport Bridge over the Allegheny River north of Pittsburgh, PA.
location
market
Client Type
The project involved the rehabilitation of an 11 span, curved girder bridge linking SR 2083 - Section A01, ramp S to SR 2037 - ramp T in Allegheny County, East Pittsburgh Borough.
location
market
Client Type
The Prettyboy Dam project involved the installation of an underwater anchorage system necessary to secure the concrete gatehouse to the dam.
location
market
Client Type
This project consisted of shoring an existing active rail that was to remain after bridge removal.
location
market
Client Type
Brayman was subcontracted to provide foundation support for the construction of the new three-building Westinghouse Global Headquarters and Education Campus located on an 83 acre parcel in Cranberry Township, PA.
location
market
Client Type
At the time one of the largest micropile projects completed in the US. Over 1600 micropiles and Low Mobility Grouting installed in karst Limestone as part of a 320 million dollar plant upgrade.
location
market
Client Type
Brayman was subcontracted to provide specialty geotechnical services in support of the construction of a new 30,000sf food storage building located in East Wheeling, WV.
location
market
Client Type
Brayman was subcontracted to provide specialty construction services in support of the Alumni Hall Addition and Renovation project at Grove City College located 65 miles north of Pittsburgh, PA.
location
market
Client Type
Work involved the installation of deep foundation systems requiring in excess of 5,000 driven H-piles (over 75 miles) and nearly 300 micropiles.
location
market
Client Type
Brayman was contracted to provide specialty construction services in support of a safety improvement project located at Paddy Creek Dam on Lake James near Nebo, NC.
location
market
Client Type
Brayman was contracted by the Black & Veatch Corporation to construct a new barge unloading and mooring facility as part of the necessary flue-gas desulfurization (FGD) upgrades at the existing Cardinal Power Station located in Brilliant, OH.
location
market
Client Type
Erected just upstream of the old bridge, the new 1096lf structure is a three-span steel haunch plate girder design carrying two lanes of traffic plus an eight-foot wide sidewalk.
location
market
Client Type
The work included the reconstruction of overpass connections to Fort Pitt Boulevard, and construction of a new three-span bridge and ramps.
location
market
Client Type
The dam received a structure upgrade in 2018, which included over 16,000-cy of mass concrete, 68-ea high capacity dam anchors, and 175-ea drains.
location
market
Client Type
The project comprised the installation of 86 caissons with diameters ranging from 30" to 54".
location
market
Client Type
The modernization effort at this site will ultimately result in the construction of two new 84-feet wide by 720-feet long chambers to replace the existing 56-feet wide lock currently in operation.
location
market
Client Type
Brayman was contracted to provide specialty construction services in support of the Dam Safety Assurance (DSA) Phase 3 Project at Bluestone Dam.
location
market
Client Type
Brayman was contracted by Songer Steel Services, Inc. to complete the concrete foundations for a new gas processing De-Ethanizer facility being constructed by a midstream operator located in Butler County, PA.
location
market
Client Type
The Pennsylvania Department of Transportation’s replacement of the SR 136 Bridge near Eighty Four, PA, was the first use of a two-span continuous fabricated structural steel precast concrete deck module system in Pennsylvania.
location
market
Client Type
The Kerr Dam Spillway Stabilization Project includes one pre-production post-tensioned rock anchor on the top of the dam, 48 production post-tensioned anchors across the downstream face of the spillway, and a temporary platform for access to the spillway locations.
location
market
Client Type
The Brayman Construction Foundations Division was subcontracted by the Tennessee Valley Authority (TVA) for specialty drilling services at the Chickamauga Dam.
location
market
Client Type
No results found.
There are no results with this criteria. Try changing your search.

Get in Touch

Interested in Partnering or Joining Our Team? Connect with us to explore opportunities for collaboration and career growth at Brayman Construction.